The Precinct on Ogilvie - January 2015

The Precinct on Ogilvie Blog

We successfully achieved our milestone of getting the top level finished and having the roof sheeted just prior to Christmas. The internal works are well underway and internal walling has progressed up to level 5, with the services trades working internally on nearly all floors of the building.

We look forward to tiling works commencing next week to level 2 and window frames also commencing in the coming weeks. The prototype apartment is well progressed and we hope to have this unit completed by the end of February.

Basement structural works are nearing completion and the focus is to have service areas ready to commence lift installation and service rooms fitouts by the end of January.

The works are tracking close to programme and can expect the builder to be complete in late June this year.

 