The Precinct on Ogilvie - April 2015

The Precinct on Ogilvie Blog

The internal finishes to the apartments are now well underway. We have finishes trades working on all the residential floors.

The externals are progressing and in two weeks time we start progressively dropping the scaffold down. While the scaffold is dropped floor by floor the final external painting and installation of the architectural fins will be completed from the scaffold.

The Commercial tenancies are now receiving some attention with external window frames being installed and internal partition walls well underway.